NASA’s Gigantic Crawler on the Move As Rollout of Mega Moon Rocket Inches Closer

Engineers and technicians at NASA’s Kennedy Space Center in Florida drove Crawler Transporter-2 on March 11, 2022 to the doors of the Vehicle Assembly Building (VAB). Soon, it will go inside the VAB where it will carry the Artemis I Moon rocket to launch pad 39B. Credit: NASA/Chad Siwik

Yesterday, engineers and technicians at NASAEstablished in 1958, the National Aeronautics and Space Administration (NASA) is an independent agency of the United States Federal Government that succeeded the National Advisory Committee for Aeronautics (NACA). It is responsible for the civilian space program, as well as aeronautics and aerospace research. It's vision is "To discover and expand knowledge for the benefit of humanity."” data-gt-translate-attributes=”[{“attribute”:”data-cmtooltip”, “format”:”html”}]”>NASA’s Kennedy Space Center in Florida drove Crawler Transporter-2, which will carry NASA’s Moon rocket to the launch pad, to the doors of the Vehicle Assembly Building (VAB). Soon, the 6.6-million-pound crawler will go inside the VAB and slide under the Space Launch System rocket and Orion spacecraft placed on the Mobile Launcher. Technicians will finish up preparations to transport the rocket traveling at a top speed of 1 mph to Launch Complex 39B for a wet dress rehearsal test ahead of the Artemis I launch.

This week, the Kennedy team also completed painting the NASA worm logo on the Space Launch System solid rocket boosters. While painters added parts of the iconic logo before the segments were stacked, they had to wait until the boosters were fully assembled to finish the job.

[embedded content]

In addition, the team has continued to retract the 20 platforms that surround the Space Launch System rocket and Orion spacecraft ahead of rollout on March 17 for the wet dress rehearsal test. The wet dress rehearsal will be the final major test for the Artemis I mission and will ensure the rocket, spacecraft, ground equipment and launch team are “go” for launch.

Coverage, Activities Set for First Rollout of NASA’s Mega Moon Rocket

NASA will hold a media teleconference on Monday, March 14 to discuss the upcoming debut of the agency’s Mega Moon rocket and integrated spacecraft for the uncrewed Artemis I lunar mission.

VAB Artemis I Space Launch System Rocket and Orion Spacecraft

Inside the Vehicle Assembly Building at NASA’s Kennedy Space Center in Florida, work platforms are being retracted from around the Artemis I Space Launch System rocket and Orion spacecraft in preparation to roll out for testing. Credit: NASA

Roll out of the integrated Space Launch System rocket and Orion spacecraft to Launch Pad 39B at NASA’s Kennedy Space Center in Florida is slated for Thursday, March 17.

The media call will begin at 5:30 p.m. EDT after completion of a test readiness review, which will determine if the agency is ready to move forward with mission activities. The call will air live on the agency’s website.

Teleconference participants include:

  • Tom Whitmeyer, associate administrator for exploration systems development, NASA Headquarters in Washington
  • Mike Sarafin, Artemis mission manager, NASA Headquarters
  • Charlie Blackwell-Thompson, Artemis launch director, NASA Exploration Ground Systems program, Kennedy
  • John Honeycutt, manager, Space Launch System program, Marshall Space Flight Center in Huntsville, Alabama
  • Howard Hu, manager, Orion program, Johnson Space Center in Houston

Live coverage for rollout begins at 5 p.m. EDT on Thursday, March 17 and will include live remarks from NASA Administrator Bill Nelson and other guests. Coverage will air on NASA Television, the NASA app, and the agency’s website. 

At the pad, NASA will conduct a final prelaunch test known as wet dress rehearsal, which includes loading the SLSNASA's Space Launch System (SLS) is part of NASA's deep space exploration plans and will launch astronauts on missions to an asteroid and eventually to Mars. As the SLS evolves, the launch vehicle will to be upgraded with more powerful versions. Eventually the SLS will have the lift capability of 130 metric tons, opening new possibilities for missions to places like Saturn and Jupiter.” data-gt-translate-attributes=”[{“attribute”:”data-cmtooltip”, “format”:”html”}]”>SLS propellant tanks and conducting a launch countdown.

The rollout involves a 4-mile journey between the Vehicle Assembly Building and the launch pad, expected to take between six and 12 hours. Live, static camera views of the debut and arrival at the pad will be available starting at 4 p.m. EDT on the Kennedy Newsroom YouTube channel.

Through Artemis missions, NASA will land the first woman and the first person of color on the Moon, paving the way for a long-term lunar presence and serving as a steppingstone on the way to MarsMars is the second smallest planet in our solar system and the fourth planet from the sun. Iron oxide is prevalent in Mars' surface resulting in its reddish color and its nickname "The Red Planet." Mars' name comes from the Roman god of war.” data-gt-translate-attributes=”[{“attribute”:”data-cmtooltip”, “format”:”html”}]”>Mars.